Berean Parking Lot

Berean Parking Lot
Project overview

Scope, delivery and field execution.

CWI was contracted to construct a new parking lot, driveways and storm systems. The work included clearing and grubbing, blasting and removal of more than 6,000 cubic yards of rock, landscape areas, stormwater management facilities and erosion-control practices designed to meet NPDES requirements.

Project typeParking Lot Expansion
ResponsibilityUpgrades
Size4.42 acres
Proposed completionAugust 2020
Actual completionAugust 2020
Original$1.45M
Final$1.79M
AccessibilityDisplay